- Joined
- 26 March 2014
- Posts
- 20,048
- Reactions
- 12,615
I've suggested that but quickly realised I ought tread carefully there.
It's a bit of an article of faith among some in very high places that no such peak will occur, at least not for a long time yet, so questioning it needs to be approached with some caution.....
My logic though is only about 50% of homes will end up installing solar. Because:
Rentals are a third of all homes and mostly won't install it.
High density generally not suitable.
Those with heavy shade or unsuitable roof designs.
Those planning to knockdown, do major renovations or replace the roof in the medium term.
Heritage listed buildings.
Those who don't have or aren't willing to invest the capital.
Those who simply don't want it.
Put that all together and my personal view is it'll top out somewhere circa 50% of homes.
WA stuff I'm no expert on but I note the gas turbines are numbered 2 and 3.I think the issue that is causing a bit more angst at the grass roots level, is the backup GT's had no 'blackstart' ability FFS.
I mean really, what intellectual midget thought that one up, FFs a major regional centre with one feeder line and the backup gen sets can't blackstart OMG. Probably saved a couple of grand in the planning phase of the project.
From AFR but it was back in feb 2023Does anyone know the status of the Kurri Kurri gas turbine plant?
It was supposed to be operational in 2023 but I can't find any recent information on it.
Mickthe 750-megawatt Kurri Kurri plant near Newcastle is now anticipated to only be fully online in December 2024, although initial power production is expected in May of that year, he said.
Current AEMO data says December 2024 for full operation, so ready in time for summer 2024-25.Does anyone know the status of the Kurri Kurri gas turbine plant?
The amount of wasted money and fossil fuel burnt for that, now where will they dig the hole to burry these..a telltale sign of a coming massive waveHas someone from WA already posted about the DeGrussa battery backup system being shut down?
Originally built to provide clean power for Sandfires DeGrussa mine, which has since closed.
From PV magazine
I wonder where all the equipment will go, and who actually owns the stuff.
According to AFR , the panels were supposed to have a life of 25 years, and its to get any metric of stats to convince that it was good investment.
Well Qld did not end up that wellCurrent AEMO data says December 2024 for full operation, so ready in time for summer 2024-25.
That said, it's likely to be physically operable some time prior to that though initially only on diesel not gas (since the pipeline is still being built).
Separate to that, all time record demand in Qld yesterday was successfully supplied. Tight, but it was supplied despite the present non-operation of Callide C and Barron Gorge power stations.
Network faults, several of them, not lack of generation.Well Qld did not end up that well
Probe ordered into mass power outage amid heatwave
An investigation has been ordered into the cause of mass power outages during a heatwave in Queensland's south-east after more than 40,000 homes lost power.www.smh.com.au
I can sense another skin of the teeth moment.Network faults, several of them, not lack of generation.
That said, two major generating units now off in Qld due to boiler tube leaks. One taken off late on Monday, other late on Tuesday.
Needless to say supply is now extremely tight especially for 27th January due to forecast weather and consumption.
I can sense another skin of the teeth moment.
113714RESERVE NOTICE24/01/2024 05:31:15 PM
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1800 hrs 27/01/2024 to 1930 hrs 27/01/2024.
The forecast capacity reserve requirement is 714 MW.
The minimum capacity reserve available is 636 MW.
AEMO is seeking a market response.
And thanks to the cyclone, 50k people or so we're not using any power..which helped the rest of Queensland.Supply was extremely tight in Queensland yesterday but no load shedding occurred due to lack of generation, those without power being so due to storm damage to networks etc. That said, it came close - discussions did commence with industry to be ready to cut load.
Supply mix as per chart.
Yellow = solar
Green = wind
Blue = hydro
Light Blue = battery
Orange = gas
Red = diesel
Black = coal
Purple = from NSW
Below the zero line during the morning and early afternoon was hydro pumping at Wivenhoe pumped storage mostly, plus a minor amount for battery charging.
View attachment 169700
Just an aside, when I type from the phone, I have a nasty spelling corrector changing my typing on enterAnd thanks to the cyclone, 50k people or so we're not using any power..which helped the rest of Queensland.
Coal is really doing a good job btw
We use cookies and similar technologies for the following purposes:
Do you accept cookies and these technologies?
We use cookies and similar technologies for the following purposes:
Do you accept cookies and these technologies?