- Joined
- 14 February 2005
- Posts
- 15,178
- Reactions
- 17,152
Answering that gets difficult in terms of the detail....Is there a similar list for the construction and start of service dates for their replacements ?
There's an abundance of interest in developing wind and solar farms, indeed there's more announcements than there are needed projects so the answer in that context is a definite "yes".
Some of those will inevitably come to nothing but overall there doesn't seem to be any major problem with getting wind and solar built so no real cause for alarm there.
To make wind and solar work as an actual alternative to fossil fuel plant however requires more than just building wind and solar farms. It requires that we also build transmission lines to connect them and to move the power to where it's required and that we build storage (batteries / hydro) or backup generation. Just building the wind and solar farms isn't all that's required.
Now for the pain.....
There's been plenty of public announcements of proposals to build storage or alternatively backup (eg gas) generation but to be blunt, not many have actually got to the point of being committed projects.
Meanwhile pretty much every major transmission project is stuck somewhere in the regulatory approvals process, even those with political support. SA - NSW, Vic - NSW upgrade, Vic - Tas second cable. Are all in the same situation as are other projects within states. Lots of promises, lots of engineers screaming that it's getting desperately urgent, still no go in terms of getting regulatory approval and without that nothing's being built.
That reality, the two paragraphs above, is what's causing all the alarm among engineers and at least the occasional politician who "gets it".
The AGL Newcastle one is a case in point. Big company that is already in the industry so should know what's involved and they already own the land and have gas infrastructure close by. Sounded like a sure thing but, it seems, perhaps not.....
Origin Shoalhaven expansion was another one that comes to mind with lots of investigation and a seemingly easy project but ultimately it's a no go.
That's just two examples but there's many, many more. Lots of pumped hydro proposals in SA and many thought the question was which one will be built first? In reality the question has ended up being whether any of them will be built at all.
Hence the concern. The building of transmission and storage (or backup generation) isn't proceeding anywhere near as quickly as it needs to and time's running short.
So what's actually a goer then?
Based on AEMO's official data, the following are "committed" and I'll add that they also happen to be physically under construction so they're pretty certain:
SA - Upgrade of existing Quarantine power station (gas), adds 20 MW of which 5 MW already completed and rest by end of 2023. Note that this does not change the closure date, it's just an improvement to the existing plant.
NSW - Upgrade of existing Bayswater power station (coal), adds 100 MW of which 25 MW already completed and rest by end of 2023. Note that this does not change the closure date, it's just improving the existing plant.
NSW - "Snowy 2.0" pumped hydro project. Capacity is nominally 2040 MW with 349,980 MWh of storage with completion stated as late 2024 - early 2025.
Victoria - "Victorian Big Battery" (that's the correct official name of it not just a colloquial one). Capacity is 300 MW power with 450 MWh of storage, so that's a 90 minute discharge time for peak load use. Completion is due before the end of 2021.
Victoria - "Bulgana Green Power Hub Battery Energy Storage System". Capacity is 20 MW with 34 MWh of storage and completion before the end of 2021.
That's it for things actually under construction.
Queensland - Kidston pumped hydro 250 MW / 2000 MWh. All the paperwork seems to finally be sorted, there should be no barrier to building it and they're about to start construction which is expected to take about 4 years to complete so that would be completion in 2025.
NSW - Australian Government has made a very high profile political commitment that a 750 MW gas (open cycle) plant will be built at Kurri Kurri. Completion is targeted before the end of 2023. Note that the site already has a sub-station and transmission line and is cleared flat land so it's as easy as it gets.
NSW - Energy Australia has made a recent high profile commitment to build a 300 MW gas (open cycle) plant alongside the existing Tallawarra power station (combined cycle) on land already owned by EA. Given the politics of it, it would be unlikely to not proceed although legally they probably could back out if they really wanted to. Completion stated as by the end of 2023.
Victoria - Upgrade to unit 2 at existing Loy Yang A power station (coal) is planned during a major outage 2025. It's not an officially "committed" project, by anyone, at this stage however. Capacity increase is 15 MW.
Tasmania - Hydro Tasmania has proposed building several pumped storage schemes and 2 x 750 MW transmission cables to Victoria with completion of the first in 2028 and the second in 2032 or thereabouts. The project stacks up economically for reasons best explained by noting the CSIRO's generation cost estimates which put pumped storage in Tasmania at just under half the cost of building the same capacity in another state. That saving covers the cost of transmission and makes it a goer financially. The problem, however, is that transmission networks are regulated and as per my comment above that process is going ever so slowly much to the frustration of many. End result is that nothing is actually being physically built at this stage despite the extensive planning and having the stated support of the Liberal and Labor parties both state and federal.
Victoria - Energy Australia has publicly "committed" to building a 350 MW / 1400 MWh battery at Jeeralang (an existing power station owned by EA) or a nearby location for operation before the end of 2026. This is however ultimately just an announcement much the same as all the others. How certain it is in the absence of development approvals, contracts etc is anyone's guess (though personally I do think this one is serious).
NSW - Greenspot is proposing to build the "Wallerawang 9 Battery" which will be a 500 MW / 1000 MW battery with completion aimed for 2023. They've gone as far as buying land from Energy Australia, which has a major substation and transmission connection on it, and engaging a demolition contractor to remove existing redundant structures at the site. They have not however signed a contract to build the battery so far as I'm aware in which case it's not "committed" in the formal sense although they would seem to be serious given they've bought land etc.
SA - SA Water proposes to build storage with a total of 15 MW and 30 MWh spread across 4 existing sites owned by SA Water. Note that these are all battery projects, not hydro, despite their location alongside water infrastructure. This project is officially classified as "emerging" and is not committed as such but has gone beyond just an announcement.
Beyond that, we're into the domain of what AEMO calls "publicly announced" and it means nothing more than that. Someone says they're going to put batteries in or build a pumped hydro scheme or whatever but that's all, it's a media release from someone. Some will end up being goers, many won't.
Summary:
Under construction = 2475 MW
Quarantine power station upgrade (gas, SA, 20 MW, 2023)
Bayswater power station upgrade (coal, NSW, 100 MW, 2023)
Snowy 2.0 pumped hydro (NSW, 2040 MW / 349,980 MWh, 2024-25)
Victorian Big Battery (Vic, 300 MW / 450 MWh, 2021)
Bulgana Green Power Hub battery (Vic, 20 MW / 34 MWh, 2021)
About to start construction = 250 MW (Kidston pumped hydro, Qld, 250 MW / 2000 MWh, 2025)
Political commitments = 1800 MW
Kurri Kurri open cycle gas turbines (NSW, 750 MW, 2023)
Tallawarra B open cycle gas turbines (NSW, 300 MW, 2023)
Tasmanian pumped hydro and Marinus Link to Victoria (Tas - Vic, 750 MW, 2028 with second 750 MW in the 2030's)
Energy Australia company public commitment = 350 MW
Jeeralang battery (Vic, 350 MW / 1400 MW, 2026)
Non-committed upgrade at existing facility = 15 MW
Loy Yang A (coal, Vic, 15 MW, 2025)
Others = 764.6 MW
Wallerawang battery (NSW, 500 MW / 1000 MWh, 2023). Looks like it's a goer but so far as I'm aware not every box has been ticked thus far. Looks promising however.
AGL Newcastle (NSW, gas, 252 MW). Anyone's guess if it'll actually happen or not.
Batteries at various sites in SA (15 MW / 30 MWh).
Beyond that = it's just media releases and announcements. Some will end up as serious projects, many won't.
So in short, some things are happening but we need to go a lot faster. Get transmission built where it's needed and get storage projects moved from merely being announced and in most cases going nowhere though to actually being built.