- Joined
- 14 February 2005
- Posts
- 15,098
- Reactions
- 16,878
Typo there on my part - should read 2030 not 2020.So we could have developed short duration pumped hydro or batteries now and completed Snowy 2.0 circa 2020
Typo there on my part - should read 2030 not 2020.So we could have developed short duration pumped hydro or batteries now and completed Snowy 2.0 circa 2020
Some raw data:So if I can ask a direction question, from a purely technical perspective disregarding politics, should the proposed gas generator be built , or are there better options ?
I guess that will be answered by Labors response, if Labor says it shouldn't be built, then if they win the next election they will have to live with the call.So if I can ask a direction question, from a purely technical perspective disregarding politics, should the proposed gas generator be built , or are there better options ?
That doesn't leave much room for spinning reserve and outage work i.e unplannedSome raw data:
Actual historic peak demand in NSW (AEMO data). All peaks occurred during summer except where indicated.
2019-20 = 13,827 MW
2018-19 = 13,861 MW
2017-18 = 13,081 MW
2016-17 = 14,107 MW
2015-16 = 13,599 MW
2014-15 = 11,874 MW
2013-14 = 12,016 MW
2012-13 = 13,906 MW
2011-12 = 12,942 MW (peak was in winter not summer)
2010-11 = 14,764 MW
So typically it's approaching 14,000 MW but there's a couple of outliers where it's significantly lower due to weather and the all time record high is 14,764 MW.
Now looking at the supply side (these figures are the summer rating where temperature is relevant):
Coal:
Bayswater = 2520 MW (closure planned for 2036)
Eraring = 2720 MW (closure 2032)
Liddell = 1680 MW (closure 1 unit 2022, other 3 in 2023)
Mt Piper = 1350 MW (remaining technical life is ~25 years)
Vales Point B = 1320 MW (closure 2029)
Combined cycle gas:
Tallawarra = 395 MW
Open cycle gas:
Colongra = 640 MW (also diesel-fired, see notes at end)
Smithfield = 107 MW
Uranquinty = 640 MW
Diesel / kerosene fuelled gas turbines:
Broken Hill = 50 MW
Hunter Valley = 30 MW (closing mid-2030's)
Eraring gas turbine = 30 MW (closing 2032) (see notes at end)
Hydro:
Blowering = 70 MW
Guthega = 68 MW
Hume = 29 MW (can be connected to either NSW or Victoria)
Shoalhaven (pumped hydro) = 240 MW
Tumut 1 = 330 MW
Tumut 2 = 286 MW
Tumut 3 (conventional hydro with 600 MW pumping capacity) = 1800 MW
Total generation NSW = 14,305 MW
Transmission Qld > NSW = 1288 MW
Transmission Vic > NSW uses the same lines as the Snowy scheme, that's what the lines were built for, such that operation of Snowy generation in NSW crowds out the ability to transfer from Victoria. Realistically though can push another 450 MW through with all Snowy plant running, considerably higher if Snowy output is lower. That assumes of course that Vic actually has the power to spare - that's far from certain and really depends on what the weather's doing and whether or not anything fails.
Total all sources = 16,043 MW not including intermittent generation (wind and solar) which may or may not generate at the time of peak demand.
Take Liddell out and that becomes 14,363 MW
Add in the planned 190 MW upgrade of transmission Qld > NSW and that brings it up to 14,553 MW
Add the 100 MW upgrade of Bayswater power station and that brings it up to 14,653 MW
Add AGL's planned 200 MW batteries (4 x 50 MW) and that brings it up to 14,853 MW
Add AGL's proposed 252 MW gas-fired peaking plant near Newcastle and that brings it up to 15,105 MW.
Comparing that to historic peak demand it could be described as right on the edge.
If everything works perfectly then the lights stay on.
Agreed - the whole situation could be described as "on the edge".That doesn't leave much room for spinning reserve and outage work i.e unplanned
Having enough capacity to reliably meet the peak is good engineering but it's poor economics to invest more $ in order to produce minimal extra revenue. That's the dilemma and so long as it's competing companies making the decisions, they're basically forced to look at the $ side first and foremost. End result is we end up with capacity that's barely adequate - that's the most financially appropriate outcome despite being far from optimum from an engineering perspective.
There's a lot of different thoughts there at the moment.Saw an article today (I think on ABC) which suggested that energy consumption will rise sharply this summer with far more people working from home and using air con.
Hello and welcome to Aussie Stock Forums!
To gain full access you must register. Registration is free and takes only a few seconds to complete.
Already a member? Log in here.