Australian (ASX) Stock Market Forum

CQT - Conquest Mining

announcement out today and surprised no postings with this one. Closed at 43.5c

ASX RELEASE
17 April 2009
Conquest to Progress Towards Production at Silver Hill
HIGHLIGHTS
● Conquest Board makes decision to proceed towards production at Silver Hill within 2 years
● Project Internal Rate of Return in excess of 70% with payback in less than 2 years
● Base case production of up to 50,000tpa of high grade concentrate and 100,000tpa of low
grade concentrate
● Net Present Value (NPV) in excess of A$300 million
● Immediate commissioning of Definitive Feasibility Study
Pre-Feasibility Study Completed
Conquest Mining Ltd (“Conquest”) (ASX:CQT) commenced a Pre-Feasibility Study (“PFS”) in 2008
on its Silver Hill gold/silver/copper deposit in North Queensland. The Company announced on 26
March 2009 that an updated resource estimate had improved confidence for the PFS.
The actual results of the completed PFS demonstrate the economics of the Silver Hill Project are
sufficiently robust and better than expected. Accordingly, Conquest is pleased to announce
approval for the commissioning of a Definitive Feasibility Study (“DFS”) prior to a final decision to
commence production at Silver Hill.
Key Findings
The key findings of the PFS which are estimates based on certain assumptions1 and
methodologies, include:
● Project Internal Rate of Return in excess of 70%
● Net Present Value (NPV) in excess of A$300 million
● Capital payback in less than 2 years of production
● Pit optimisation of 6 million tonnes (Mt) with mine life in excess of 6 years
● Processing capacity up to 1 million tonnes per annum (Mtpa) to produce a high grade
gold/silver/copper concentrate plus a low grade concentrate
● High grade concentrate grades of 60 g/t gold, 1000 g/t silver and 10% copper
● Base case production of up to 50,000 tpa of high grade concentrate and 100,000 tpa of low
grade concentrate
● Bulk of precious metals to be available for sale in a high grade concentrate. The remainder will
be produced from a low grade concentrate processed on site2.
● Effective gold equivalent production of 800,000oz with an annual average gold equivalent
production of 135,000oz
● Gold equivalent production made up of 72% Gold, 15% Silver & 13% Copper
● Life of mine operating costs of less than A$400/oz
● Upfront pre-production capital cost of approximately A$110m
1. Pre-tax assuming US$900/oz Au, US$12.50/oz Ag, US$4,000/tonne Cu and a FX of US$0.70 to A$1.00
2. Extraction of valuable metals in the Low Grade material will include the application of bio oxidation
These PFS findings clearly demonstrate the outstanding returns expected from development of the
Silver Hill Project, indicating an estimated cash operating cost of less than A$400/oz for
annualised production of 135,000oz gold equivalent over a mine life in excess of 6 years with
estimated pre-production capital cost of A$110 million.
Independent Consultants
Preparation and validation of the PFS has been done with the assistance of reputable independent
consultants overseen by Conquest. These independent consultants include:
- Mine Design and Cost estimation - AustralAsian Resource Consultants (AARC), Australian
Mine Design & Development and Optiro Pty Ltd
- Flotation Design and Cost estimation - AARC and Calder’s Engineering
- GEOCOAT ® Design and Cost estimation: - GeoBiotics and Mike Gunn
- Geology and Resource Model - Hellman & Schofield
- Metallurgy - GRD Minproc & AMTEC
- Environmental Impact Study – AARC
- Market and pricing - CRU
- Financial model development - Azure Capital
Off-Take Arrangements
As announced on 1 April 2009, Conquest has also materially progressed discussions with potential
off-take counterparties. Conquest is confident it can negotiate off-take contracts (on acceptable
terms) in the medium term.
Summary
The rigour and maturity of analysis reflected in the PFS through various iterations of the project
have provided the Board with sufficient comfort to immediately proceed to the next stage of project
development. Conquest will now commission a DFS to further confirm the findings of the PFS as
well as to seek to optimise the project to increase potential returns.
In the coming months, Conquest will define the timing of completion of the DFS and, subject to the
results of that study, the anticipated timing for production commencement at Silver Hill. It is
currently anticipated production will commence within 2 years. The Company will advise on more
 
Up 19% today to close at 52.50c and big volume. Seems a quite stock with not much interest but 19% does indicate that some is at least interested.
 
This is an interesting stock with some positive announcements lately. Looks like theres reasonable support around 47c.

Anyone else following this one? It does seem unusually quite at times given the price action.
 
just recently researched this company and so far so good, i like it.they are in a good land position, in close proximity to the 10m oz charters towers and with results due very soon for the next round of drilling perhaps this is one to get on for the ride.
 
Wow - Cant belieive no posts on this for a year now. New board including the old SinoGold boys and have just acquired NQM (Northern Queensland Mines).
 
Top