Re: HOG - also what is a go in the time to come ....
Permission already granted for the
Chernetska project.
In addition to the works at Sorochynska, Hawkley is in the process of preparing for the first well at Chernetska. A full project update on Chernetska will be provided soon. The current timetable is as follows:
Well plan – approved
Environmental approval - granted
Land access - granted
Drilling contract – completed
Pipe, casing, mud, additives, drilling bits etc contracts and supply – in progress
Site preparation – commenced
Drilling rig mobilisation – after Christmas
In order to accelerate the progress of the well ahead of revenue from Sorochynska Well #201, Hawkley has secured a loan facility of US$1.25 million. The purpose of the loan is to facilitate the site preparation and the building of a road ahead of rig up early next year.
Cheers form The Netherlands
Permission already granted for the
Chernetska project.
In addition to the works at Sorochynska, Hawkley is in the process of preparing for the first well at Chernetska. A full project update on Chernetska will be provided soon. The current timetable is as follows:
Well plan – approved
Environmental approval - granted
Land access - granted
Drilling contract – completed
Pipe, casing, mud, additives, drilling bits etc contracts and supply – in progress
Site preparation – commenced
Drilling rig mobilisation – after Christmas
In order to accelerate the progress of the well ahead of revenue from Sorochynska Well #201, Hawkley has secured a loan facility of US$1.25 million. The purpose of the loan is to facilitate the site preparation and the building of a road ahead of rig up early next year.