Good news from CEO with latest ASX statement today-
Power station construction on track
5MW power station construction due for
completion by end of December
Queensland Government representative to
officiate at Bloodwood Creek event
Plans for the next phase – a 20MW facility
incorporating CCS – are underway
>
>
>
“In July we commenced the construction of our 5MW power plant, which we
aim to have up and operational prior to the end of December, with electricity
following into the local grid by January next year.
We set ourselves an extremely ambitious target of six months (July-
December) to disassemble the generating equipment from its Victorian
location, build the new foundations at our Queensland site, transport the
equipment, reassemble, test and commission, ready to connect to the local
electricity network.
The power station, when commissioned, will be fuelled by gas produced from
our Underground Coal Gasification (UCG) panel constructed last year and
it’s important to recognise that this will be the first power facility of its type in
Australia.
I am pleased to say we are currently on track and I have outlined the major
construction milestones below.
Due to the flurry of activity in July, getting the 5MW project up and running, we
did not have the opportunity to do any type of official launch function, so this
is now planned for 19th November. I am pleased to say that the Honourable
Michael Choi Parliamentary Secretary to the Minister for Natural Resources,
Water & Energy will be officiating at our Mid Construction Launch.
Whilst the 5MW plant is an important first phase project for Carbon Energy, we
are already well progressed with our Phase 2 project, an additional 20-25 MW
power plant, which will incorporate carbon capture and storage technology.
Front-end engineering and design (FEED) is now underway with the initial
report due in December.
This is an exciting project as it will position Carbon Energy at the forefront of
the world-wide quest for low emission energy from coal.
As you can see it’s been a busy few months and I look forward to keeping you
updated on our progress.”
Regards
Andrew
Managing Director
Andrew Dash
Power station construction on track
5MW power station construction due for
completion by end of December
Queensland Government representative to
officiate at Bloodwood Creek event
Plans for the next phase – a 20MW facility
incorporating CCS – are underway
>
>
>
“In July we commenced the construction of our 5MW power plant, which we
aim to have up and operational prior to the end of December, with electricity
following into the local grid by January next year.
We set ourselves an extremely ambitious target of six months (July-
December) to disassemble the generating equipment from its Victorian
location, build the new foundations at our Queensland site, transport the
equipment, reassemble, test and commission, ready to connect to the local
electricity network.
The power station, when commissioned, will be fuelled by gas produced from
our Underground Coal Gasification (UCG) panel constructed last year and
it’s important to recognise that this will be the first power facility of its type in
Australia.
I am pleased to say we are currently on track and I have outlined the major
construction milestones below.
Due to the flurry of activity in July, getting the 5MW project up and running, we
did not have the opportunity to do any type of official launch function, so this
is now planned for 19th November. I am pleased to say that the Honourable
Michael Choi Parliamentary Secretary to the Minister for Natural Resources,
Water & Energy will be officiating at our Mid Construction Launch.
Whilst the 5MW plant is an important first phase project for Carbon Energy, we
are already well progressed with our Phase 2 project, an additional 20-25 MW
power plant, which will incorporate carbon capture and storage technology.
Front-end engineering and design (FEED) is now underway with the initial
report due in December.
This is an exciting project as it will position Carbon Energy at the forefront of
the world-wide quest for low emission energy from coal.
As you can see it’s been a busy few months and I look forward to keeping you
updated on our progress.”
Regards
Andrew
Managing Director
Andrew Dash