That's right Syd.
Not yet a year in office for the Coalition compared to 6-years for Labor and their Minister of Missed Targets. There's a long way to go yet before any meaningful comparison can be made.
I don't think there's too many even within Labor now that bow at the shrine of Stephen Conroy.
http://www.afr.com/p/technology/nbn_work_grinds_to_halt_in_some_8xnphrriSnRSZMDQNEzL0O
But analysis of statistics from the company reveal that most of the progress has been in NSW, Victoria and Queensland. The *rollout has dramatically slowed down in all other states and territories.
In Tasmania, Western Australia, South Australia and ACT, only 141 existing homes and businesses have been passed with fibre-optic cabling since June 30 – an average of just 21 premises per week across all four states and territories.
South Australia has been one of the hardest hit, with 86 new brownfield premises passed since March 23 – an average of just 4.2 homes and businesses per week.
In contrast, NBN Co has passed an average of 952 premises per week in Victoria over the same period.
The ACT’s brownfield premises passed count has remained stagnant since June 2014 with a weekly average of 2.4 premises passed over the past six and a half weeks.
The national rate of construction has also slowed down. Where the rollout was hitting an average of 4152 existing premises passed per week in the six months ending June 30, it has slowed to 2714 premises per week since then.