Re: GBE - Globe Uranium
DFS Update – Kanyika Niobium Project
Globe provide an update on progress towards completion of the Kanyika Definitive Feasibility Study (DFS) and implementation of the Kanyika Niobium Project in Malawi. The DFS is progressing according to schedule with the achievement of a number of key milestones this quarter including:
● Completion and submission of the Environmental Impact Assessment (EIA) for all areas of the Project. A copy is available for review here:
www.globemetalsandmining.com.au.
● Completion of the processing flowsheet development with variability testing and proof of concept underway.
● Advancement of the process plant design and completion of the infrastructure, tailings storage facility and wastemanagement design concepts.
● Issue of tenders for the project early works program, including the main access road, project fencing and accommodation villages.
● Advancement of project financing with a Letter of Intent from China Development Bank in place.
● Development of a Social Responsibility Plan as part of the EIA, with several programs already underway.
● Completion of the Project area census and commencement of the Relocation Action Plan.
● Advancement of marketing studies, with off-take agreements in negotiation and the first MoUs in place.
● The infill drilling program is due for completion in August, which will deliver an upgraded resource of more than 50 Mt in Measured and Indicated categories with a mine life of more than 20 years.
The project economics remain attractive and the DFS is on track for completion to draft level in December 2012. This will allow Globe to make the project commitment decision in February 2013. Globe has commenced negotiations with the Government of Malawi towards finalising the Project Development Agreement and hopes to produce the first ferro-niobium at Kanyikain late 2014, early 2015.